Ms. Quirk asks about the backlog of fire hydrant maintenance and the timeframe for its reduction. The Minister provides figures showing a reduction since 2008 and anticipates further reduction by January.

AnsweredQoN 6099Legislative Assembly
Asked
8 September 2011
Portfolio
Water

QuestionView source ↗

(1) What is the current backlog for maintenance of fire hydrants?
(2) What time frame is required to reduce that backlog?

AnswerView source ↗

Answered
18 October 2011
Responded by
Minister for Water
Response time
40 days
(1) At 20 September 2011, there were 859 outstanding hydrant work orders. This represents a reduction of 404 since June 2008 when there were 1263 hydrant work orders outstanding.
(2) It is anticipated that the number of outstanding work orders will reduce to approximately 300 by January next year.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more