Hon Michael Mischin questions the Minister for Education and Training regarding the Halidon Primary School administration building upgrade, specifically seeking advice related to the project's initiation and progress. The Minister provides information on funding and project timeline, referencing previous questions on the matter.

AnsweredQoN 864Legislative Council
Asked
20 September 2018
Portfolio
Education and Training

QuestionView source ↗

HALIDON PRIMARY SCHOOL — ADMINISTRATION
BUILDING UPGRADE
864. Hon MICHAEL MISCHIN to the Minister for Education and
Training:
I refer to the administration
building project at Halidon Primary School, which arose out of an election
commitment by the member for Kingsley.
(1) Can the
minister produce and table a copy of any advice she received in her capacity as
minister —
(a) regarding
that commitment and prompting the project to be undertaken by the Department of
Education; and
(b) regarding the
progress and completion of that project?
(2) If not, why not?

AnswerView source ↗

I thank the honourable member for
some notice of the question.
(1) (a) This
project was funded through the Local Projects, Local Jobs program. Again, I refer
the member to Legislative Council questions without notice 570, 575, 616, 620
and 683, as well as Legislative Council question on notice 1578.
(b) The work
comprised a redevelopment of the current administration building. It was commenced
on December 2017 and it was completed in January 2018.
(2) Not applicable.