❓ A WA parliamentary question seeks details about the Rottnest Island Authority's approved proposal, funding, timeline, contractor, and tendering process for the army jetty redevelopment. The answer provides some details on approved works and funding, but lacks specific dates and contractor information.
AnsweredQoN 1769Legislative Council
Asked
8 November 2018
Member
Portfolio
Tourism; Racing and Gaming; Small Business; Defence Issues; Citizenship and Multicultural Interests
QuestionView source ↗
(1) What
specific proposal was approved by the Board of the Rottnest Island Authority
for the army jetty redevelopment? (2) What
amount of funding was approved? (3) As
at 24 October 2018, when was the redevelopment of the army jetty scheduled to
commence? (4) As
at 24 October 2018, when was the redevelopment of the army jetty scheduled to
be complete? (5) Who
was undertaking the redevelopment of the army jetty? (6) Was
the redevelopment of the army jetty advertised for tender on Tenders WA
website: (a) if no to (6), why not?
specific proposal was approved by the Board of the Rottnest Island Authority
for the army jetty redevelopment? (2) What
amount of funding was approved? (3) As
at 24 October 2018, when was the redevelopment of the army jetty scheduled to
commence? (4) As
at 24 October 2018, when was the redevelopment of the army jetty scheduled to
be complete? (5) Who
was undertaking the redevelopment of the army jetty? (6) Was
the redevelopment of the army jetty advertised for tender on Tenders WA
website: (a) if no to (6), why not?
AnswerView source ↗
Answered
6 December 2018
Responded by
Minister for Regional Development representing the Minister for Tourism; Racing and Gaming; Small Business; Defence Issues; Citizenship and Multicultural Interests
Response time
9 days
(1) Upgrade works and re-instatement of barge landing on the end of the former Army Jetty, on condition that management provides a fully costed redevelopment proposal for examination by the Board and undertake community consultation on the project.
(2) $400,000 for the upgrade works and re-instatement of barge landing.
(3-6) Approved works were to commence when the Board’s conditions had been met and would have been subject to State Government procurement processes.
(2) $400,000 for the upgrade works and re-instatement of barge landing.
(3-6) Approved works were to commence when the Board’s conditions had been met and would have been subject to State Government procurement processes.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.