❓ A WA parliamentary question seeks updated cost and completion estimates for the Southern Suburbs Railway (Perth to Mandurah Railway) project. The answer provides current figures and notes upcoming budget and timing reviews.
AnsweredQoN 519Legislative Assembly
QuestionView source ↗
(b) what is the most up-to-date estimate of the total interest costs associated with borrowings used to fund the entire project; and (c) what is the most up-to-date estimate of the completion date for the entire project?
(c) what is the most up-to-date estimate of the completion date for the entire project?
This figure will be reviewed as part of the budget process. (b) The current estimate of the total cost of interest on the capital borrowings attributable to the Southern Suburbs Railway over 33 years is $1,151,000,000 (c) The current timing for completion of the Southern Suburbs Railway is April 2007. This timing will be reviewed in early 2006.
(b) The current estimate of the total cost of interest on the capital borrowings attributable to the Southern Suburbs Railway over 33 years is $1,151,000,000 (c) The current timing for completion of the Southern Suburbs Railway is April 2007. This timing will be reviewed in early 2006.
(c) The current timing for completion of the Southern Suburbs Railway is April 2007. This timing will be reviewed in early 2006.
(c) what is the most up-to-date estimate of the completion date for the entire project?
This figure will be reviewed as part of the budget process. (b) The current estimate of the total cost of interest on the capital borrowings attributable to the Southern Suburbs Railway over 33 years is $1,151,000,000 (c) The current timing for completion of the Southern Suburbs Railway is April 2007. This timing will be reviewed in early 2006.
(b) The current estimate of the total cost of interest on the capital borrowings attributable to the Southern Suburbs Railway over 33 years is $1,151,000,000 (c) The current timing for completion of the Southern Suburbs Railway is April 2007. This timing will be reviewed in early 2006.
(c) The current timing for completion of the Southern Suburbs Railway is April 2007. This timing will be reviewed in early 2006.
AnswerView source ↗
Answered
7 March 2006
Responded by
Minister for Planning and Infrastructure
Response time
104 days
(a) The current estimate of the total capital cost of the Perth to Mandurah Railway (Southern Suburbs Railway), allowing for the distribution of overhead costs and rollingstock, is $1,321,144,000.
This figure will be reviewed as part of the budget process.
(b) The current estimate of the total cost of interest on the capital borrowings attributable to the Southern Suburbs Railway over 33 years is $1,151,000,000
(c) The current timing for completion of the Southern Suburbs Railway is April 2007. This timing will be reviewed in early 2006.
This figure will be reviewed as part of the budget process.
(b) The current estimate of the total cost of interest on the capital borrowings attributable to the Southern Suburbs Railway over 33 years is $1,151,000,000
(c) The current timing for completion of the Southern Suburbs Railway is April 2007. This timing will be reviewed in early 2006.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.