Hon. Alanna Clohesy asks about funding, scope, consultation, and timeline for the proposed Great Eastern Highway Bilgoman-Mundaring bicycle path. The parliamentary secretary provides details on funding, construction scope, consultation with the Shire of Mundaring, and project timeline.

AnsweredQoN 728Legislative Council
Asked
18 June 2015
Portfolio
Transport

QuestionView source ↗

GREAT
EASTERN HIGHWAY — BILGOMAN–MUNDARING BICYCLE PATH
728. Hon ALANNA CLOHESY to the
parliamentary secretary representing the Minister for Transport:
I refer to the minister's recent media statement
regarding new bike paths.
(1) How much
funding has been allocated to the proposed Great Eastern Highway Bilgoman–Mundaring
path?
(2) What is the scope of works of this proposed path?
(3) Who has been consulted on the development of the proposed
path?
(4) When will construction commence and when will it be
completed?
The PRESIDENT : The minister for bike transport—sorry;
I meant the parliamentary secretary representing the Minister for Transport!

AnswerView source ↗

It was a Freudian slip, Mr President! I thank the honourable
member for some notice of the question.
(1) The amount is $400 000.
(2) It is to
construct 2.2 kilometres of path adjacent to the eastbound carriageway from
Kintore Road to Mann Street, Mundaring, and 400 metres adjacent to the
westbound carriageway from Hardey Road to McGlew Road.
(3) It was the Shire of Mundaring.
(4) Preconstruction
works for the 7.2-kilometre upgrade of Great Eastern Highway are proposed to
commence in 2015–16, with completion in 2017–18.