Hon. Donna Faragher asks about the planning, timeline, and cost of the proposed new primary school in Burns Beach. The Minister responds that planning hasn't commenced, the project will start in 2020-21, and $15.6 million is budgeted, but the total cost is not finalised.

AnsweredQoN 1214Legislative Council
Asked
23 October 2019
Portfolio
Education and Training

QuestionView source ↗

NEW PRIMARY SCHOOL —
BURNS BEACH
1214. Hon DONNA FARAGHER to the Minister for Education and
Training:
I refer to the proposed new primary
school in Burns Beach.
(1) Has planning commenced for the
construction of the new school?
(2) If yes to (1), will the
minister provide a construction time line for the new school?
(3) What is the expected total
project cost of the school building program at full stage completion?

AnswerView source ↗

I thank the honourable member for
some notice of the question.
(1) No. As per the 26 October 2017
media statement, the project will commence in 2020–21.
(2) Not applicable.
(3) The
department currently has a budget of $15.6 million allocated for this school.
The total project cost is yet to be finalised.