Mrs. Harvey inquires about the completion, authorship, and public availability of the review regarding delays on the Forrestfield-Airport Link. The Minister confirms the report's completion and publication on the project website.

AnsweredQoN 5171Legislative Assembly
Asked
16 May 2019
Portfolio
Transport

QuestionView source ↗

I refer to the delays on the Forrestfield-Airport Link, and I ask: (a) Has the review now been completed; (b) If yes to (a), who undertook the review; (c) Will the Minister table the review; and (d) If no to (c), why not?

AnswerView source ↗

Answered
18 June 2019
Responded by
Minister for Transport
Response time
7 days
(a)-(d) The report to the Minister – Cross Passage Dundas incident and rectification works – was completed in December 2018. Following the 18 December 2018 media conference where the revised project timeline was announced, the report was published on the Forrestfield-Airport Link website.

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more