❓ Mrs. Harvey inquires about the completion, authorship, and public availability of the review regarding delays on the Forrestfield-Airport Link. The Minister confirms the report's completion and publication on the project website.
AnsweredQoN 5171Legislative Assembly
QuestionView source ↗
I refer to the delays on the Forrestfield-Airport Link, and I ask: (a) Has the review now been completed; (b) If yes to (a), who undertook the review; (c) Will the Minister table the review; and (d) If no to (c), why not?
AnswerView source ↗
Answered
18 June 2019
Responded by
Minister for Transport
Response time
7 days
(a)-(d) The report to the Minister – Cross Passage Dundas incident and rectification works – was completed in December 2018. Following the 18 December 2018 media conference where the revised project timeline was announced, the report was published on the Forrestfield-Airport Link website.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.