❓ Hon Peter Collier asks about the status of the Australian Marine Complex strategic infrastructure and land use plan, including completion date, tabling, and contract variations. The Minister responds that the plan is in development, with a draft expected in Q1 2020, and acknowledges a contract variation for an infrastructure report.
AnsweredQoN 1490Legislative Council
QuestionView source ↗
AUSTRALIAN MARINE COMPLEX
STRATEGIC INFRASTRUCTURE AND LAND USE PLAN
1490. Hon PETER COLLIER to
the minister representing the Minister for Defence Issues:
I
refer to the contract awarded to Advisian for the provision of the Australian
Marine Complex strategic infrastructure and land use plan.
(1) Has the plan been completed?
(2) If yes to (1), will the
minister table the plan; and, if not, why not?
(3) If no to (1), when is the plan
expected to be completed?
(4) Have there been any variations
to the contract?
(5) If yes to (4), what was the
cost and what was the reason for the variations?
STRATEGIC INFRASTRUCTURE AND LAND USE PLAN
1490. Hon PETER COLLIER to
the minister representing the Minister for Defence Issues:
I
refer to the contract awarded to Advisian for the provision of the Australian
Marine Complex strategic infrastructure and land use plan.
(1) Has the plan been completed?
(2) If yes to (1), will the
minister table the plan; and, if not, why not?
(3) If no to (1), when is the plan
expected to be completed?
(4) Have there been any variations
to the contract?
(5) If yes to (4), what was the
cost and what was the reason for the variations?
AnswerView source ↗
I thank the member for the
question. The following information has been provided to me by the Minister for
Defence Issues.
(1) The Australian Marine Complex
strategic infrastructure and land use plan is in development.
(2) Not applicable.
(3) The draft
plan is expected to be completed in the first quarter of 2020 for further
stakeholder consultation.
(4) Yes.
(5) The
infrastructure report on full cycle docking requirements was a variation, with
a cost of $65 868, including GST.
question. The following information has been provided to me by the Minister for
Defence Issues.
(1) The Australian Marine Complex
strategic infrastructure and land use plan is in development.
(2) Not applicable.
(3) The draft
plan is expected to be completed in the first quarter of 2020 for further
stakeholder consultation.
(4) Yes.
(5) The
infrastructure report on full cycle docking requirements was a variation, with
a cost of $65 868, including GST.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.