WA Parliamentary Question on Notice regarding reviews, inquiries, committees, and taskforces established within the Mines and Petroleum portfolio since 23 September 2008. The response details one inquiry into upstream petroleum safety regulation and an Industry Working Group on Approvals.

AnsweredQoN 126Legislative Council
Asked
26 November 2008
Portfolio
Mines and Petroleum

QuestionView source ↗

(1) Since 23 September 2008, what, -
(a) reviews;
(b) inquiries;
(c) committees; and
(d) taskforces,
have been established?
(2) What was the start date and also the expected completion date for each, -
(a) review;
(b) inquiry;
(c) committee; and
(d) taskforce?
(3) Who chairs each, -
(a) review;
(b) inquiry;
(c) committee; and
(d) taskforce?
(4) What is the estimated budget for each, -
(a) review;
(b) inquiry;
(c) committee; and
(d) taskforce?

AnswerView source ↗

Answered
9 March 2009
Responded by
Minister for Mines and Petroleum
Response time
103 days
The Ministrial office
(1) (a) Nil
(b) On the 23 December 2008, the Commonwealth and WA Governments announced that a jointly conducted inquiry would be undertaken into the effectiveness of safety regulation for upstream petroleum operations with a focus on the incident at Apache Energy Ltd's facilities on Varanus Island.
(c) Industry Working Group on Approvals
(d) Nil
(2) (a) Not applicable
(b) The inquiry will commence late January 2009 and a report is expected within 3 months of the commencement of the inquiry.
(c) The Industry Working Group on Approvals was formed via ministerial announcement on 17 November 2008 and completion is due end April 2009.
(d) Not applicable
(3) (a) Not applicable
(b) The inquiry will be conducted by a two-member expert panel i.e. David Agostini (State appointed) and Kym Bills (Commonwealth appointed)
(c) Chairman - Hon Peter Jones AM, former Resources Minister in the Sir Charles Court Government (retired).
(d) Not applicable
(4) (a) Not applicable
(b) Funding for the inquiry will be met by the Commonwealth Government and capped at $1 million.
(c) Funding for the Working Group is limited to secretariat support which will be provided by the Department of Mines and Petroleum. Total costs are estimated at $100,000.
(d) Not applicable.
the DEPARTMENT OF MINES AND PETROLEUM
(1) (a) - (d) None.
(2) (a) - (d) N/A
(3) (a) - (d) N/A
(4) (a) - (d) N/A
MERIWA
(1) (a) - (d) None.
(2) (a) - (d) N/A
(3) (a) - (d) N/A
(4) (a) - (d) N/A
Chemistry Centre
No review, inquiry, committee or taskforce has been established by or through the ChemCentre in the relevant time frame.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more