❓ WA Parliamentary Question on Notice regarding planned intersection improvements and passing lane/truck bay construction on Toodyay Road, including timelines and cost estimates. The answer provides details on design, construction, and funding for these projects.
AnsweredQoN 514Legislative Assembly
QuestionView source ↗
(b) when in each year will the works be commenced and completed; and (c) for each project, what is the estimated cost and how much has currently been allocated (if a different amount)?
(c) for each project, what is the estimated cost and how much has currently been allocated (if a different amount)?
Intersection Improvements :- Improvements planned at the intersection of Toodyay Road and Roland Road, involve cutting the embankment to improve sight lines. Design to be prepared in the period November 2005 to June 2006 and, subject to aboriginal and environmental clearances, construction planned for October to December 2007. Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program. Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Improvements planned at the intersection of Toodyay Road and Roland Road, involve cutting the embankment to improve sight lines. Design to be prepared in the period November 2005 to June 2006 and, subject to aboriginal and environmental clearances, construction planned for October to December 2007. Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program. Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Design to be prepared in the period November 2005 to June 2006 and, subject to aboriginal and environmental clearances, construction planned for October to December 2007. Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program. Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program. Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
· Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
· Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
· Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
(c) for each project, what is the estimated cost and how much has currently been allocated (if a different amount)?
Intersection Improvements :- Improvements planned at the intersection of Toodyay Road and Roland Road, involve cutting the embankment to improve sight lines. Design to be prepared in the period November 2005 to June 2006 and, subject to aboriginal and environmental clearances, construction planned for October to December 2007. Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program. Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Improvements planned at the intersection of Toodyay Road and Roland Road, involve cutting the embankment to improve sight lines. Design to be prepared in the period November 2005 to June 2006 and, subject to aboriginal and environmental clearances, construction planned for October to December 2007. Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program. Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Design to be prepared in the period November 2005 to June 2006 and, subject to aboriginal and environmental clearances, construction planned for October to December 2007. Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program. Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program. Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Three Passing Lanes & One Truck Bay :- · Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
· Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill · Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
· Passing lane eastbound near Stoneville Rd · Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
· Passing lane eastbound near Berry Rd Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M. Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
AnswerView source ↗
Answered
3 January 2006
Responded by
Minister for Planning and Infrastructure
Response time
41 days
(a) - (c) The following works are planned on Toodyay Road over the period
30 June 2006 through to 30 June 2009.
Intersection Improvements
:-
Improvements planned at the intersection of Toodyay Road and Roland Road, involve cutting the embankment to improve sight lines.
Design to be prepared in the period November 2005 to June 2006 and, subject to aboriginal and environmental clearances, construction planned for October to December 2007.
Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program.
Three Passing Lanes & One Truck Bay
:-
· Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill
· Passing lane eastbound near Stoneville Rd
· Passing lane eastbound near Berry Rd
Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M.
Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
30 June 2006 through to 30 June 2009.
Intersection Improvements
:-
Improvements planned at the intersection of Toodyay Road and Roland Road, involve cutting the embankment to improve sight lines.
Design to be prepared in the period November 2005 to June 2006 and, subject to aboriginal and environmental clearances, construction planned for October to December 2007.
Preliminary cost estimate is $150 000 with funding to be sought from the 2006/07 and 2007/08 State Black Spot Program.
Three Passing Lanes & One Truck Bay
:-
· Passing lane (connecting two existing passing lanes) and Truck Bay, eastbound at the top of Red Hill
· Passing lane eastbound near Stoneville Rd
· Passing lane eastbound near Berry Rd
Tenders for this work closed on 25 November 2005 with the lowest price in the order of $3.3M.
Construction of the passing lanes near Stoneville Rd and Berry Rd expected to be undertaken during February-May 2006 and work on the passing lane and truck bay at Red Hill planned for October-December 2006.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.