Hon Ken Travers asks about the estimated cost of a Perth to Bunbury fast train, and the Minister for Transport provides a breakdown of preliminary infrastructure costs from a 2010 feasibility study.

AnsweredQoN 2941Legislative Council
Asked
20 October 2010
Portfolio
Transport

QuestionView source ↗

(1) Have any of the studies into the feasibility of a fast train from Perth to Bunbury, provided an estimation of the cost of this project?
(2) If yes to (1), -
(a) what is the estimated cost for the project; and
(b) what were the main assumptions used in estimated the cost?

AnswerView source ↗

Answered
23 November 2010
Responded by
Minister for Transport
Response time
34 days
(1) Yes. Preliminary planning costs for infrastructure only were provided through the Final Report titled Perth to Bunbury Fast Train Feasibility Study January 2010 undertaken for the Public Transport Authority by consultants GHD. Appendix C of this report outlines these costs.
(2)
(a) Preliminary estimated infrastructure costs expressed in the last quarter of 2009 dollar values are as follows -
Perth Underground to Eaton with grade separation of Forrest Highway Road interchanges $872 million;
Eaton to Bunbury City with grade separation of roads $110 million; and
additional cost for an electric railway from Perth Underground to Bunbury City $195 million.
(b) The estimated cost is an attempt to give a realistic understanding of the actual cost by providing the engineering feasibility, defining a preferred route having investigated several options with regard to environmental, social, land use, risk and other criteria. These are fully described in the Final Report.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more