A parliamentary question regarding the monitoring and remediation of contamination at the Cristal Global plant in Australind, and the potential for an environmental bond. The government response indicates monitoring is occurring and remediation is underway, but an environmental bond is not deemed necessary.

AnsweredQoN 5731Legislative Council
Asked
19 June 2012
Portfolio
Environment

QuestionView source ↗

In relation to the Cristal Global plant located on government land at Lot 4 Old Coast Road Australind, I ask —
(1) Is this site monitored by the Department of Conservation and Environment (DEC)?
(2) If no to (1), why not?
(3) Has the Minister any evidence that the company has commenced rehabilitation of the contaminated areas on the site?
(4) What steps has DEC taken to ensure that remediation and rehabilitation is taking place on this site?
(5) Is the Government considering applying an environmental bond on Cristal Globe to safeguard against long term contamination?
(6) If no to (5), why not?

AnswerView source ↗

Answered
14 August 2012
Responded by
Minister for Mental Health representing the Minister for Environment
Response time
56 days
(1)-(2) The chemical manufacturing plant at Lot 4 Old Coast Road, Australind is licensed under Part V of the
Environmental Protection Act 1986
and is also classified
contaminated - remediation required
under the
Contaminated Sites Act 2003
. The Department of Environment and Conservation (DEC) monitors compliance with the licence conditions and also monitors progress with contamination investigations and remediation.
(3) The licensee reports on progress with its contaminated groundwater recovery and treatment program in its Annual Environmental Report, submitted in accordance with its licence conditions.
(4) Prior to the commencement of the Contaminated SitesAct, the premises' licence included reporting requirements on the groundwater recovery and treatment program. Contamination investigation and remediation at the site are now regulated under the Contaminated Sites Act, and DEC monitors progress with these works.
(5) No
(6) The licensee has taken voluntary action since 1978 to recover and treat contaminated groundwater, indicating that a financial assurance need not be applied in this instance. DEC will ensure that the licensee continues to make satisfactory progress with investigation, remediation, management and monitoring of contamination at the site.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more