Question regarding offsite storage of building materials for Fiona Stanley Hospital and associated costs. The answer indicates no additional storage costs were incurred as the spares were part of the original construction contract.

AnsweredQoN 986Legislative Assembly
Asked
6 August 2013
Portfolio
Health

QuestionView source ↗

I refer to the construction and fit out of the Fiona Stanley Hospital, and the various building materials purchased for the hospital, and ask:
(a) have any building materials, finishing or interior fittings been purchased that have been required to be stored offsite and what were these materials; and
(b) for each material, I ask:
(i) how long has it been in storage;
(ii) what is the cost to date for the storage of each material; and
(iii) what is the estimated total cost of storing each material?

AnswerView source ↗

Answered
10 September 2013
Responded by
Minister for Health
Response time
35 days
(b)(i) 12 - 18 months but the spares are of a non-perishable nature i.e. spare façade panels, air-conditioning plant, etc. (ii-iii) Nil as these spares were always required to be provided under the Construction Works Contract.
(ii-iii) Nil as these spares were always required to be provided under the Construction Works Contract.