THOMPSON STREET, WILUNA — HOUSING DEVELOPMENT
I refer to the housing development in Thompson Street, Wiluna, funded by royalties for regions; the answer to a question without notice asked on 30 August 2011 of the Minister for Housing; and the Kalgoorlie Miner article of 22 September 2011 entitled “Cost blow-out for housing ‘debacle’”. (1) Why did the development blow out by $257 000? (2) What is the estimated cost of the damage sustained by these houses? (3) Why is the Department of Housing’s Government Regional Officers’ Housing revenue funding picking up the shortfall, not the royalties for regions fund? (4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN
I refer to the housing development in Thompson Street, Wiluna, funded by royalties for regions; the answer to a question without notice asked on 30 August 2011 of the Minister for Housing; and the Kalgoorlie Miner article of 22 September 2011 entitled “Cost blow-out for housing ‘debacle’”. (1) Why did the development blow out by $257 000? (2) What is the estimated cost of the damage sustained by these houses? (3) Why is the Department of Housing’s Government Regional Officers’ Housing revenue funding picking up the shortfall, not the royalties for regions fund? (4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN
AnswerView source ↗
I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(1) Why did the development blow out by $257 000? (2) What is the estimated cost of the damage sustained by these houses? (3) Why is the Department of Housing’s Government Regional Officers’ Housing revenue funding picking up the shortfall, not the royalties for regions fund? (4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(2) What is the estimated cost of the damage sustained by these houses? (3) Why is the Department of Housing’s Government Regional Officers’ Housing revenue funding picking up the shortfall, not the royalties for regions fund? (4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(3) Why is the Department of Housing’s Government Regional Officers’ Housing revenue funding picking up the shortfall, not the royalties for regions fund? (4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(6) Practical completion is scheduled for 2012.
(1) Why did the development blow out by $257 000? (2) What is the estimated cost of the damage sustained by these houses? (3) Why is the Department of Housing’s Government Regional Officers’ Housing revenue funding picking up the shortfall, not the royalties for regions fund? (4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(2) What is the estimated cost of the damage sustained by these houses? (3) Why is the Department of Housing’s Government Regional Officers’ Housing revenue funding picking up the shortfall, not the royalties for regions fund? (4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(3) Why is the Department of Housing’s Government Regional Officers’ Housing revenue funding picking up the shortfall, not the royalties for regions fund? (4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(4) Why was no licence to build these buildings required from the Shire of Wiluna? (5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(5) Who was responsible for the oversight of these constructions? (6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(6) When will the construction recommence or has the construction recommenced? Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
Hon SIMON O’BRIEN replied: I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
I thank the member for some notice of the question. (1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(1) The additional costs to complete these properties arise from works required to finalise construction and associated remedial work. (2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(2) There is no estimated cost of damage. The repair of any damage incurred is included in the costs to complete construction. (3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(3) The department will endeavour to cover any extra costs through the project budget, which was funded by royalties for regions. (4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(4) The department has obtained a building compliance certificate for these dwellings in accordance with the legislated process. (5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(5) The Department of Housing was responsible. (6) Practical completion is scheduled for 2012.
(6) Practical completion is scheduled for 2012.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.