Dr. Constable inquires about the cost, quantity, and completion timeline for proposed boat pens in Challenger and Bunbury Boat Harbours. The response provides the number of pens and expected completion dates, but omits the estimated cost.

AnsweredQoN 1227Legislative Assembly
Asked
7 November 2001
Portfolio
Planning and Infrastructure

QuestionView source ↗

(1) What is the estimated cost of the proposed additional boat pens in the Challenger Boat Harbour and Bunbury Boat Harbour?
(2) How many pens will be constructed in each location?
(3) When will they be completed?

AnswerView source ↗

Answered
29 November 2001
Responded by
Minister for Planning and Infrastructure
Response time
22 days
(2) Challenger 55 Casuarina 60 (the pens at Challenger Harbour will be for larger vessels) (3) Subject to obtaining all necessary approvals, completion for each project is expected as follows: Challenger July 2002 Casuarina October 2002
(3) Subject to obtaining all necessary approvals, completion for each project is expected as follows: Challenger July 2002 Casuarina October 2002
Challenger July 2002 Casuarina October 2002