❓ Question regarding funding and completion date of the Esperance Waterfront project, a priority in the Esperance Super Town Growth Plan. The answer provides funding details for 2012 and the expected completion date.
AnsweredQoN 2207Legislative Assembly
QuestionView source ↗
I refer to the “Esperance Waterfront”, listed as a priority project in the Esperance Super Town Growth Plan and ask: (a) how much funding has the project received for the financial years: (i) 2011–2012; and (ii) 2012–2013; (b) how much funding has been allocated for the project for the financial years: (i) 2013–2014; (ii) 2014–2015; and (iii) 2016–2017; and (c) what is the expected completion date for the project?
AnswerView source ↗
Answered
8 May 2014
Responded by
Minister for Regional Development
Response time
28 days
(a) (i)-(ii) On 29 June 2012, $12 650 417 was deposited into the relevant Shire account for the Esperance Waterfront Project.
(c) The anticipated project completion date is 20 August 2014.
(c) The anticipated project completion date is 20 August 2014.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.