Question on Notice regarding the Margaret River Perimeter Road, inquiring about the alignment, environmental approvals, and preliminary design status. The responses indicate the project is still in the planning and approval stages.

AnsweredQoN 5012Legislative Council
Asked
9 November 2011
Portfolio
Transport

QuestionView source ↗

I refer to the Margaret River Perimeter Road, and ask -
(1) Has an alignment been agreed for the perimeter road?
(2) If yes to (1), will the Minister table a map showing the alignment?
(3) If no to (1), when does the Minister expect the alignment to be finalised?
(4) Has the Government secured State and Federal environmental approvals for the project?
(5) If no to (4), what is the timeline for securing these approvals?
(6) Has the preliminary design for the perimeter road been finalised?
(7) If no to (6), when will it be finalised?
(8) If yes to (6), will the Minister table it?

AnswerView source ↗

Answered
5 March 2012
Responded by
Minister for Finance representing the Minister for Transport
Response time
117 days
Main Roads WA
advisesas at 9 November 2011:
(1) No
(2) Not applicable
(3) In the first half of 2012.
(4) No
(5) Expected in 2013.
(6) No, as it requires finalisation of the alignment.
(7) Expected in 2012.
(8) Not applicable
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more