Hon Sue Ellery asks about a variation to the Roe Highway Stage 8 contract, specifically regarding the Roe Highway-Stock Road interchange and its cost. The Parliamentary Secretary confirms the variation and cost, clarifying there's no new contract.

AnsweredQoN 1216Legislative Council
Asked
8 November 2016
Portfolio
Transport

QuestionView source ↗

ROE HIGHWAY STAGE 8 — CONTRACT VARIATION
1216. Hon SUE ELLERY to the parliamentary
secretary representing the Minister for Transport:
I refer to the confirmation in the
annual report estimates hearing last week that a variation has been signed on
the Roe 8 contract.
(1) Please detail what the variation
is and what the total cost was?
(2) Will the minister table the new
contract in full?

AnswerView source ↗

I thank the honourable member for
some notice of the question.
(1) The variation
is to include the Roe Highway–Stock Road interchange in the scope of
works, at a cost of $109 million.
(2) There is no new contract. The
Roe 8 contract was tabled in Parliament on 20 October 2016.