KWINANA FREEWAY —
WIDENING
183. Hon PETER COLLIER to
the minister representing the Minister for Transport:
I refer to question without notice
23 answered on 12 February 2020.
(1) Will the
minister now provide the date of practical completion for the project when the
contract was first signed; and, if not, why not?
(2) What specific
early works for the Metronet Thornlie–Cockburn Link were integrated
into the Kwinana Freeway northbound widening project?
(3) What is the cost of these
works?
(4) Have these works now been
completed; and, if not, when will the works be completed?
WIDENING
183. Hon PETER COLLIER to
the minister representing the Minister for Transport:
I refer to question without notice
23 answered on 12 February 2020.
(1) Will the
minister now provide the date of practical completion for the project when the
contract was first signed; and, if not, why not?
(2) What specific
early works for the Metronet Thornlie–Cockburn Link were integrated
into the Kwinana Freeway northbound widening project?
(3) What is the cost of these
works?
(4) Have these works now been
completed; and, if not, when will the works be completed?
AnswerView source ↗
I thank the Leader of the
Opposition for some notice of the question. The following answer has been
provided by the Minister for Transport.
(1) At the time the contract was
first signed, practical completion for all works was 30 September 2020.
(2) There were drainage and median
barrier works, including retaining structures.
(3) The cost is $6.7 million.
(4) It is
anticipated that these works will be completed by mid-July 2020, although the
staged opening of new northbound freeway lanes is expected to be completed by
April 2020.
Opposition for some notice of the question. The following answer has been
provided by the Minister for Transport.
(1) At the time the contract was
first signed, practical completion for all works was 30 September 2020.
(2) There were drainage and median
barrier works, including retaining structures.
(3) The cost is $6.7 million.
(4) It is
anticipated that these works will be completed by mid-July 2020, although the
staged opening of new northbound freeway lanes is expected to be completed by
April 2020.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.