Hon Martin Pritchard asks about the progress of the Perth Stadium pedestrian bridge design and fabrication tender process. The Minister confirms design documentation is incomplete but quotes have been requested from fabricators, with completion expected by December 2015.

AnsweredQoN 951Legislative Council
Asked
10 September 2015
Portfolio
Transport

QuestionView source ↗

PERTH
STADIUM — PEDESTRIAN BRIDGE
951. Hon MARTIN PRITCHARD to
the parliamentary secretary representing the Minister for Transport:
I refer to questions without notice 246, 694 and 823 in
relation to the proposed stadium footbridge.
(1) Has the
contractor completed design documentation so that procurement details can be
finalised; and, if so —
(a) will tenders for fabrication
of structural elements be advertised; and, if so, when; and
(b) if no to
(a), why not, given the ministerXXX ###XXXs commitment
in his answer to question without notice 823?
(2) If design documentation has not been completed —
(a) when is it expected to be
completed; and
(b) when are tenders for
fabrication expected to be advertised?

AnswerView source ↗

I thank the honourable member for some notice of this
question.
(1) No. Design documentation has not been completed.
(a) The
contractor has requested quotes from 15 steel fabricators. Approximately half
of these fabricators are Australian businesses, including several from Western
Australia. The contractor will finalise a fabrication order once the final
design has been confirmed.
(b) See (a).
(2) NovemberQQQ ### QQQDecember 2015.