❓ Great Northern Highway—Bindoon Bypass 721. Hon Julie Freeman to the parliamentary secretary representing the Minister for Transport: I refer to the much-anticipated Great Northern Highway—Bindoon Bypa
AnsweredQoN 721Legislative Council
QuestionView source ↗
Great Northern Highway—Bindoon Bypass
721. Hon Julie Freeman to
the parliamentary secretary representing the
Minister for Transport:
I refer to the much-anticipated Great Northern Highway—Bindoon
Bypass.
(1) Is the northern section of the bypass complete
and, if not, what is the revised timeline for its completion?
(2) Has land acquisition for the southern section
of the bypass been completed and, if not, when is it expected to be finalised?
(3) At the time of the 2024–25 budget
estimates, Main Roads Western Australia was undertaking a review to see whether
additional funding was required; is the review complete?
(4) If yes to (3), what is the revised cost of the
project?
721. Hon Julie Freeman to
the parliamentary secretary representing the
Minister for Transport:
I refer to the much-anticipated Great Northern Highway—Bindoon
Bypass.
(1) Is the northern section of the bypass complete
and, if not, what is the revised timeline for its completion?
(2) Has land acquisition for the southern section
of the bypass been completed and, if not, when is it expected to be finalised?
(3) At the time of the 2024–25 budget
estimates, Main Roads Western Australia was undertaking a review to see whether
additional funding was required; is the review complete?
(4) If yes to (3), what is the revised cost of the
project?
AnswerView source ↗
I thank the honourable member for some notice of the
question. I provide the following answer on behalf of the Minister for
Transport.
(1) The northern section is expected to be
completed by mid-2026.
(2) The Bindoon South land take is complete; price
negotiations are still progressing.
(3) The review is ongoing, with an estimate to be
undertaken prior to commencement of the procurement process for the southern
section.
(4) Not applicable.
question. I provide the following answer on behalf of the Minister for
Transport.
(1) The northern section is expected to be
completed by mid-2026.
(2) The Bindoon South land take is complete; price
negotiations are still progressing.
(3) The review is ongoing, with an estimate to be
undertaken prior to commencement of the procurement process for the southern
section.
(4) Not applicable.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.