Mrs. Hayden requests a detailed breakdown of the $33 million Rottnest Island makeover funding, specifying project costs, start, and completion dates. The answer provides a breakdown of state and federal funded projects with timelines and budgets.

AnsweredQoN 6266Legislative Assembly
Asked
17 June 2020
Portfolio
Tourism; Racing and Gaming; Small Business; Defence Issues; Citizenship and Multicultural Interests

QuestionView source ↗

I refer to the announcement in April 2019 that Rottnest Island was to receive a $33 million makeover after a State and Federal funding boost, and ask: (a) Can you please provide a breakdown of this expenditure by project, including: (i) start and completion dates; and (ii) costs of each individual project?

AnswerView source ↗

Answered
11 August 2020
Responded by
Minister for Tourism; Racing and Gaming; Small Business; Defence Issues; Citizenship and Multicultural Interests
Response time
5 days
(a)(i)-(ii):
Start (a)(i)
Completion (a)(i)
Budget (a)(ii)
State Funded Marine Projects
Fuel Jetty
Underway
By November 2020
$3.0 million
Main Jetty
Required to be completed by June 2023
$4.0 million
Barge Ramp at South Thomson
$9.15 million
Total Stated Funded
$16.15 million
Federal Funded Projects
City of York (public space)
Underway
All projects are required to be completed by April 2022
$0.6 million
Oliver Hill (public space)
$0.4 million
West End (public space)
$2.0 million
Wadjemup Hill (public space/ buildings / ablutions)
$2.6 million
Wayfinding (signage)
$0.6 million
Island Gateway (museum / public space)
$4.5 million
The Basin (public space / ablutions)
$1.5 million
Accommodation (buildings / refurbishment)
$5.0 million
Total Federal Funded
$17.2 million
Total Project Funding
$33.35 million