❓ Mrs. Hayden requests a detailed breakdown of the $33 million Rottnest Island makeover funding, specifying project costs, start, and completion dates. The answer provides a breakdown of state and federal funded projects with timelines and budgets.
AnsweredQoN 6266Legislative Assembly
Asked
17 June 2020
Member
Portfolio
Tourism; Racing and Gaming; Small Business; Defence Issues; Citizenship and Multicultural Interests
QuestionView source ↗
I refer to the announcement in April 2019 that Rottnest Island was to receive a $33 million makeover after a State and Federal funding boost, and ask: (a) Can you please provide a breakdown of this expenditure by project, including: (i) start and completion dates; and (ii) costs of each individual project?
AnswerView source ↗
Answered
11 August 2020
Responded by
Minister for Tourism; Racing and Gaming; Small Business; Defence Issues; Citizenship and Multicultural Interests
Response time
5 days
(a)(i)-(ii):
Start (a)(i)
Completion (a)(i)
Budget (a)(ii)
State Funded Marine Projects
Fuel Jetty
Underway
By November 2020
$3.0 million
Main Jetty
Required to be completed by June 2023
$4.0 million
Barge Ramp at South Thomson
$9.15 million
Total Stated Funded
$16.15 million
Federal Funded Projects
City of York (public space)
Underway
All projects are required to be completed by April 2022
$0.6 million
Oliver Hill (public space)
$0.4 million
West End (public space)
$2.0 million
Wadjemup Hill (public space/ buildings / ablutions)
$2.6 million
Wayfinding (signage)
$0.6 million
Island Gateway (museum / public space)
$4.5 million
The Basin (public space / ablutions)
$1.5 million
Accommodation (buildings / refurbishment)
$5.0 million
Total Federal Funded
$17.2 million
Total Project Funding
$33.35 million
Start (a)(i)
Completion (a)(i)
Budget (a)(ii)
State Funded Marine Projects
Fuel Jetty
Underway
By November 2020
$3.0 million
Main Jetty
Required to be completed by June 2023
$4.0 million
Barge Ramp at South Thomson
$9.15 million
Total Stated Funded
$16.15 million
Federal Funded Projects
City of York (public space)
Underway
All projects are required to be completed by April 2022
$0.6 million
Oliver Hill (public space)
$0.4 million
West End (public space)
$2.0 million
Wadjemup Hill (public space/ buildings / ablutions)
$2.6 million
Wayfinding (signage)
$0.6 million
Island Gateway (museum / public space)
$4.5 million
The Basin (public space / ablutions)
$1.5 million
Accommodation (buildings / refurbishment)
$5.0 million
Total Federal Funded
$17.2 million
Total Project Funding
$33.35 million
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.