Hon Donna Taylor asks about the funding and completion date for the Reid Highway extension. Hon Adele Farina provides the committed funding, allocation across financial years, and expected completion date.

AnsweredQoN 428Legislative Council
Asked
29 June 2005
Portfolio
Planning and Infrastructure

QuestionView source ↗

I refer to the extension of Reid Highway between West Swan Road and Great Northern Highway. (1) What total funding has been committed to complete this extension? (2) Of that total funding, what funding has been allocated in 2004-05 and 2005-06, and in the forward estimates for 2006-07, 2007-08 and 2008-09? (3) What is the expected date of completion of this extension? Hon ADELE FARINA

AnswerView source ↗

I thank the member for some notice of this question. (1) The total funding is $27 million. (2) Funding for the project is allocated in the following years under the Safer Roads program: 2005-06, $1.5 million; 2006-07, $5.5 million; and 2007-08, $20.2 million. (3) Completion is expected in 2008.
(1) What total funding has been committed to complete this extension? (2) Of that total funding, what funding has been allocated in 2004-05 and 2005-06, and in the forward estimates for 2006-07, 2007-08 and 2008-09? (3) What is the expected date of completion of this extension? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The total funding is $27 million. (2) Funding for the project is allocated in the following years under the Safer Roads program: 2005-06, $1.5 million; 2006-07, $5.5 million; and 2007-08, $20.2 million. (3) Completion is expected in 2008.
(2) Of that total funding, what funding has been allocated in 2004-05 and 2005-06, and in the forward estimates for 2006-07, 2007-08 and 2008-09? (3) What is the expected date of completion of this extension? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The total funding is $27 million. (2) Funding for the project is allocated in the following years under the Safer Roads program: 2005-06, $1.5 million; 2006-07, $5.5 million; and 2007-08, $20.2 million. (3) Completion is expected in 2008.
(3) What is the expected date of completion of this extension? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The total funding is $27 million. (2) Funding for the project is allocated in the following years under the Safer Roads program: 2005-06, $1.5 million; 2006-07, $5.5 million; and 2007-08, $20.2 million. (3) Completion is expected in 2008.
Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The total funding is $27 million. (2) Funding for the project is allocated in the following years under the Safer Roads program: 2005-06, $1.5 million; 2006-07, $5.5 million; and 2007-08, $20.2 million. (3) Completion is expected in 2008.
I thank the member for some notice of this question. (1) The total funding is $27 million. (2) Funding for the project is allocated in the following years under the Safer Roads program: 2005-06, $1.5 million; 2006-07, $5.5 million; and 2007-08, $20.2 million. (3) Completion is expected in 2008.
(1) The total funding is $27 million. (2) Funding for the project is allocated in the following years under the Safer Roads program: 2005-06, $1.5 million; 2006-07, $5.5 million; and 2007-08, $20.2 million. (3) Completion is expected in 2008.
(2) Funding for the project is allocated in the following years under the Safer Roads program: 2005-06, $1.5 million; 2006-07, $5.5 million; and 2007-08, $20.2 million. (3) Completion is expected in 2008.
(3) Completion is expected in 2008.