A WA parliamentary question on notice regarding the cost and timeline of the Southern Suburbs Railway project, specifically addressing tunnelling progress under William Street.

AnsweredQoN 552Legislative Assembly
Asked
1 December 2005
Portfolio
Planning and Infrastructure

QuestionView source ↗

(b) when will the project be completed; (c) how much tunnelling under William Street has been undertaken; and (d) when will the tunnelling be completed?
(c) how much tunnelling under William Street has been undertaken; and (d) when will the tunnelling be completed?
(d) when will the tunnelling be completed?
(b) The current time for completion of the Southern Suburbs Railway is April 2007. (c) Bored tunnelling carried out as at 1 December 2005 is 105 metres. (d) The current time for completion of bored tunnelling under William Street is the end of November 2006.
(c) Bored tunnelling carried out as at 1 December 2005 is 105 metres. (d) The current time for completion of bored tunnelling under William Street is the end of November 2006.
(d) The current time for completion of bored tunnelling under William Street is the end of November 2006.

AnswerView source ↗

Answered
3 January 2006
Responded by
Minister for Planning and Infrastructure
Response time
33 days
(a) The current total cost of the Perth to Mandurah Railway, (Southern Suburbs Railway) including its allocation of overhead costs and the distributed cost for rollingstock is $1,320.86 million. The current total expected cost of the New MetroRail Project is $1,563.372 million.
(b) The current time for completion of the Southern Suburbs Railway is April 2007.
(c) Bored tunnelling carried out as at 1 December 2005 is 105 metres.
(d) The current time for completion of bored tunnelling under William Street is the end of November 2006.