Hon Wendy Duncan asks about the Hopetoun-Ravensthorpe waste water treatment scheme's total cost and completion timeline. The Minister responds with the cost of stage 1 and a completion date of April 2009.

AnsweredQoN 514Legislative Council
Asked
29 May 2008
Portfolio
Water Resources

QuestionView source ↗

HOPETOUN-RAVENSTHORPE WASTE WATER TREATMENT SCHEME
Given that the budget papers refer to estimated expenditure of just $6 million in 2008-09 for the Hopetoun-Ravensthorpe waste water treatment scheme — (1) Can the minister please detail the total cost of all stages of this crucial project? (2) Can the minister provide a time line for its completion? Hon KIM CHANCE

AnswerView source ↗

I thank Hon Wendy Duncan for providing some notice of the question. The Minister for Water Resources has provided the following response — (1) The total cost of the Hopetoun waste water scheme stage 1, including the $6 million in the 2008-09 budget, is $16 million. (2) The gravity sewer, pump station and treatment works are scheduled to be completed in April 2009. The contractor is on site and works are in progress.
(1) Can the minister please detail the total cost of all stages of this crucial project? (2) Can the minister provide a time line for its completion? Hon KIM CHANCE replied: I thank Hon Wendy Duncan for providing some notice of the question. The Minister for Water Resources has provided the following response — (1) The total cost of the Hopetoun waste water scheme stage 1, including the $6 million in the 2008-09 budget, is $16 million. (2) The gravity sewer, pump station and treatment works are scheduled to be completed in April 2009. The contractor is on site and works are in progress.
(2) Can the minister provide a time line for its completion? Hon KIM CHANCE replied: I thank Hon Wendy Duncan for providing some notice of the question. The Minister for Water Resources has provided the following response — (1) The total cost of the Hopetoun waste water scheme stage 1, including the $6 million in the 2008-09 budget, is $16 million. (2) The gravity sewer, pump station and treatment works are scheduled to be completed in April 2009. The contractor is on site and works are in progress.
Hon KIM CHANCE replied: I thank Hon Wendy Duncan for providing some notice of the question. The Minister for Water Resources has provided the following response — (1) The total cost of the Hopetoun waste water scheme stage 1, including the $6 million in the 2008-09 budget, is $16 million. (2) The gravity sewer, pump station and treatment works are scheduled to be completed in April 2009. The contractor is on site and works are in progress.
I thank Hon Wendy Duncan for providing some notice of the question. The Minister for Water Resources has provided the following response — (1) The total cost of the Hopetoun waste water scheme stage 1, including the $6 million in the 2008-09 budget, is $16 million. (2) The gravity sewer, pump station and treatment works are scheduled to be completed in April 2009. The contractor is on site and works are in progress.
(1) The total cost of the Hopetoun waste water scheme stage 1, including the $6 million in the 2008-09 budget, is $16 million. (2) The gravity sewer, pump station and treatment works are scheduled to be completed in April 2009. The contractor is on site and works are in progress.
(2) The gravity sewer, pump station and treatment works are scheduled to be completed in April 2009. The contractor is on site and works are in progress.