❓ Mr. Papalia questions the Minister for Transport regarding the cost of the Warnbro bus facility upgrade project, which has significantly exceeded the initial budget. The Minister provides the total cost as of June 30, 2013, and the projected completion costs.
AnsweredQoN 888Legislative Assembly
QuestionView source ↗
The 2011–2012 Budget Papers , in the section Rail Stations Improvement program, outlined upgrading the Warnbro bus facilities, with additional parking to the southern end of the station at a cost of $2.7 million in 2011–2012, will the Minister outline: (a) outline the total cost of the project as of 30 June 2013; and (b) provide the projected costs for the completion of the project?
AnswerView source ↗
Answered
2 September 2013
Responded by
Minister for Transport
Response time
67 days
The
Public Transport Authority
advises:
(a) $5.57m
(b) $5.63m
Public Transport Authority
advises:
(a) $5.57m
(b) $5.63m
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.