❓ Hon. Darren West questions the Minister for Transport regarding funding and planning for the Bindoon deviation project within the Great Northern Highway Muchea-Wubin stage 2 works. The Minister confirms a corridor has been identified but funding is not yet allocated and land acquisition hasn't commenced.
AnsweredQoN 605Legislative Council
QuestionView source ↗
BINDOON
DEVIATION
605. Hon DARREN WEST to the
parliamentary secretary representing the Minister for Transport:
I refer to the $81 million allocated
in the 2014–15 budget for works on Great Northern Highway, Muchea–Wubin
stage 2.
(1) Will the
works and allocation within stage 2 include funding and construction of the
Bindoon deviation?
(2) Has the corridor for the Bindoon
deviation been identified?
(3) What is the
total amount required for the Bindoon deviation; and, of that amount, how much
has been allocated for the acquisition of land?
(4) Has any land been acquired in
advance of the work?
(5) When is work likely to commence?
DEVIATION
605. Hon DARREN WEST to the
parliamentary secretary representing the Minister for Transport:
I refer to the $81 million allocated
in the 2014–15 budget for works on Great Northern Highway, Muchea–Wubin
stage 2.
(1) Will the
works and allocation within stage 2 include funding and construction of the
Bindoon deviation?
(2) Has the corridor for the Bindoon
deviation been identified?
(3) What is the
total amount required for the Bindoon deviation; and, of that amount, how much
has been allocated for the acquisition of land?
(4) Has any land been acquired in
advance of the work?
(5) When is work likely to commence?
AnswerView source ↗
I thank the honourable member for
some notice of the question.
(1) No.
(2) Yes, a corridor been identified.
(3) Main Roads
has called for tenders for an integrated project services consultancy to
conduct a planning study that recommends treatment and priorities for upgrade
of all remaining sections of Great Northern Highway from Muchea to Wubin. This
study will assess the costs and the staging options for the Bindoon deviation,
including land acquisition.
(4) No.
(5) Not applicable.
some notice of the question.
(1) No.
(2) Yes, a corridor been identified.
(3) Main Roads
has called for tenders for an integrated project services consultancy to
conduct a planning study that recommends treatment and priorities for upgrade
of all remaining sections of Great Northern Highway from Muchea to Wubin. This
study will assess the costs and the staging options for the Bindoon deviation,
including land acquisition.
(4) No.
(5) Not applicable.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.