The Government confirms its support for a new bus-rail interchange at Karnup, estimating it may be required around 2025. A cost estimate exists from 2011 but needs updating.

AnsweredQoN 1637Legislative Council
Asked
11 September 2014
Portfolio
Transport

QuestionView source ↗

(1) Does the Government still support a new bus–rail interchange at Karnup? (2) If yes to (1): (a) when does the Government expect it will be needed; and (b) what is the current estimated cost?

AnswerView source ↗

Answered
15 October 2014
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
34 days
(1) Yes, at the appropriate time.
(2)(a) Timing will be influenced by land use and land take-up; currently it is estimated the interchange may be required around 2025.
(b) A cost estimate was undertaken in 2011 based on a very preliminary concept design and would need to be updated as part of the progression of this project at the appropriate time.