Hon Martin Aldridge asks about the progress of the Albany radiation oncology service redevelopment, specifically regarding timelines, budget, and expenditure. The Minister's response indicates the project is on track and within budget.

AnsweredQoN 652Legislative Council
Asked
5 April 2022
Portfolio
Health

QuestionView source ↗

I refer to the media statement of 21 April 2021 entitled “Successful tender announced for lifesaving
Albany radiation oncology service", and I ask: (a) will the Minister please provide detail of the current timeline of this
redevelopment; (b) is the
project on track to be completed in the second half of 2022; (c) can
the Minister confirm what funds have been spent on the project to date; and (d) is the
project total cost expected to exceed the $13.1 million originally budgeted?

AnswerView source ↗

Answered
10 May 2022
Responded by
Leader of the House representing the Minister for Health
Response time
3 days
a)      The works are currently in construction. Expected Practical Completion of building is early September 2022.
b)      Yes.
c)      As at 31 March 2022 is $6,978,126 (excluding GST).
d)      No.