Mr. McGowan inquires about the timeline, financial contributions, and reasons for potential lack of funding for a marina project. The Minister responds with updates on land use negotiations, timeline uncertainty, allocated funding for planning, and a 'not applicable' response.

AnsweredQoN 347Legislative Assembly
Asked
9 August 2000
Member
Portfolio
Transport

QuestionView source ↗

(b) when does the Government expect the relevant issues in relation to the marina to be finalised; (c) will the Government be contributing any financial resources towards this project; and (d) if not, why not?
(c) will the Government be contributing any financial resources towards this project; and (d) if not, why not?
(d) if not, why not?

AnswerView source ↗

Answered
17 October 2000
Response time
69 days
The Minister Replied:
(a) The Department of Transport and the Department of Land Adminstration are endeavouring to resolve restrictions on land use with the Commonwealth in order for the project to proceed.
(b) It is not possible to be definite. All avenues are being pursued to resolve the land issues quickly.
(c) Funding of $100 000 has been provided to the Department of Transport in the current budget to progress the planning issues on the project.
(d) Not applicable.