❓ A WA parliamentary question seeks information about the Office of Water Strategy's staffing, structure, and funding. The response provides details on staff numbers, positions, senior staff names, and funding for 2005-06, but indicates a change in funding allocation for 2006-07.
AnsweredQoN 666Legislative Assembly
QuestionView source ↗
With reference to the Office of Water Strategy, I ask -
(1) How many staff are employed?
(2) What is the title and level of each position?
(3) What are the names and titles of the four most senior staff?
(4) What is the allocated funding for 2005-2006 and 2006-2007?
(1) How many staff are employed?
(2) What is the title and level of each position?
(3) What are the names and titles of the four most senior staff?
(4) What is the allocated funding for 2005-2006 and 2006-2007?
AnswerView source ↗
Answered
2 May 2006
Responded by
Minister for Water Resources
Response time
35 days
(1) 13 (2) Director, Class 1 - currently vacant Principal Policy Officer, Level 8 (x2) - one position currently vacant Senior Project Manager, Level 7 Senior Policy Officer, Level 6 (x5) - 3 positions temporary; 2 positions currently vacant Senior Project Officer, Level 6 (x3) Temporary Public Affairs Officer, Level 6 - currently vacant Project Officer, Level 5 Project and Grant Officer, Level 4 Temporary Administrative Assistant, Level 2 (x2) Officer, Level 1 (3) M Rowe, A/Principal Policy Officer S Gunning, Senior Project Manager M Yrke, Senior Policy Officer E Yuen, Senior Policy Officer (4) 2005-06: $6.88m 2006-07: Funding for the work previously undertaken by the Office of Water Strategy will be allocated to the Department of Water through the 2006-07 budget process.
(2) Director, Class 1 - currently vacant Principal Policy Officer, Level 8 (x2) - one position currently vacant Senior Project Manager, Level 7 Senior Policy Officer, Level 6 (x5) - 3 positions temporary; 2 positions currently vacant Senior Project Officer, Level 6 (x3) Temporary Public Affairs Officer, Level 6 - currently vacant Project Officer, Level 5 Project and Grant Officer, Level 4 Temporary Administrative Assistant, Level 2 (x2) Officer, Level 1 (3) M Rowe, A/Principal Policy Officer S Gunning, Senior Project Manager M Yrke, Senior Policy Officer E Yuen, Senior Policy Officer (4) 2005-06: $6.88m 2006-07: Funding for the work previously undertaken by the Office of Water Strategy will be allocated to the Department of Water through the 2006-07 budget process.
(3) M Rowe, A/Principal Policy Officer S Gunning, Senior Project Manager M Yrke, Senior Policy Officer E Yuen, Senior Policy Officer (4) 2005-06: $6.88m 2006-07: Funding for the work previously undertaken by the Office of Water Strategy will be allocated to the Department of Water through the 2006-07 budget process.
(4) 2005-06: $6.88m 2006-07: Funding for the work previously undertaken by the Office of Water Strategy will be allocated to the Department of Water through the 2006-07 budget process.
(2) Director, Class 1 - currently vacant Principal Policy Officer, Level 8 (x2) - one position currently vacant Senior Project Manager, Level 7 Senior Policy Officer, Level 6 (x5) - 3 positions temporary; 2 positions currently vacant Senior Project Officer, Level 6 (x3) Temporary Public Affairs Officer, Level 6 - currently vacant Project Officer, Level 5 Project and Grant Officer, Level 4 Temporary Administrative Assistant, Level 2 (x2) Officer, Level 1 (3) M Rowe, A/Principal Policy Officer S Gunning, Senior Project Manager M Yrke, Senior Policy Officer E Yuen, Senior Policy Officer (4) 2005-06: $6.88m 2006-07: Funding for the work previously undertaken by the Office of Water Strategy will be allocated to the Department of Water through the 2006-07 budget process.
(3) M Rowe, A/Principal Policy Officer S Gunning, Senior Project Manager M Yrke, Senior Policy Officer E Yuen, Senior Policy Officer (4) 2005-06: $6.88m 2006-07: Funding for the work previously undertaken by the Office of Water Strategy will be allocated to the Department of Water through the 2006-07 budget process.
(4) 2005-06: $6.88m 2006-07: Funding for the work previously undertaken by the Office of Water Strategy will be allocated to the Department of Water through the 2006-07 budget process.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.