INDIGENOUS EARLY CHILDHOOD NATIONAL PARTNERSHIP IMPLEMENTATION PLAN — CHILDREN AND FAMILY CENTRES
I refer to the children and family centres under the Indigenous Early Childhood National Partnership Implementation Plan for WA and ask — (1) Have the agreed milestones for the reporting period January to June 2011 been met for the centres to be constructed in — (a) Halls Creek; (b) Fitzroy Crossing; and (c) Kununurra? (2) Is it anticipated that the agreed milestones for the reporting period July to December 2011 will be met for the centres to be constructed in: (a) Halls Creek; (b) Fitzroy Crossing; (c) Kununurra; (d) Roebourne; and (e) Swan? Hon PETER COLLIER

AnswerView source ↗

I thank the honourable member for some notice of this question. I am advised by the Department of Education as follows— (1) (a) In Halls Creek, the service model is finalised—100 per cent; governance structure is finalised—100 per cent; construction is completed—100 per cent; and the operator selection process is partially completed—95 per cent. (b) In Fitzroy Crossing, all agreed milestones have been met. (c) In Kununurra, all agreed milestones have been met. (2) (a) In Halls Creek, it is anticipated that all agreed milestones will be met. (b) In Fitzroy Crossing, it is anticipated that construction will be completed by January–June 2012. (c) In Kununurra, the building tender has been awarded, with construction anticipated January–June 2012. (d) In Roebourne, it is anticipated that all agreed milestones will be met. (e) In Swan, it is anticipated that all agreed milestones will be met.
(1) Have the agreed milestones for the reporting period January to June 2011 been met for the centres to be constructed in — (a) Halls Creek; (b) Fitzroy Crossing; and (c) Kununurra? (2) Is it anticipated that the agreed milestones for the reporting period July to December 2011 will be met for the centres to be constructed in: (a) Halls Creek; (b) Fitzroy Crossing; (c) Kununurra; (d) Roebourne; and (e) Swan? Hon PETER COLLIER replied: I thank the honourable member for some notice of this question. I am advised by the Department of Education as follows— (1) (a) In Halls Creek, the service model is finalised—100 per cent; governance structure is finalised—100 per cent; construction is completed—100 per cent; and the operator selection process is partially completed—95 per cent. (b) In Fitzroy Crossing, all agreed milestones have been met. (c) In Kununurra, all agreed milestones have been met. (2) (a) In Halls Creek, it is anticipated that all agreed milestones will be met. (b) In Fitzroy Crossing, it is anticipated that construction will be completed by January–June 2012. (c) In Kununurra, the building tender has been awarded, with construction anticipated January–June 2012. (d) In Roebourne, it is anticipated that all agreed milestones will be met. (e) In Swan, it is anticipated that all agreed milestones will be met.
I thank the honourable member for some notice of this question. I am advised by the Department of Education as follows— (1) (a) In Halls Creek, the service model is finalised—100 per cent; governance structure is finalised—100 per cent; construction is completed—100 per cent; and the operator selection process is partially completed—95 per cent. (b) In Fitzroy Crossing, all agreed milestones have been met. (c) In Kununurra, all agreed milestones have been met. (2) (a) In Halls Creek, it is anticipated that all agreed milestones will be met. (b) In Fitzroy Crossing, it is anticipated that construction will be completed by January–June 2012. (c) In Kununurra, the building tender has been awarded, with construction anticipated January–June 2012. (d) In Roebourne, it is anticipated that all agreed milestones will be met. (e) In Swan, it is anticipated that all agreed milestones will be met.
(1) (a) In Halls Creek, the service model is finalised—100 per cent; governance structure is finalised—100 per cent; construction is completed—100 per cent; and the operator selection process is partially completed—95 per cent. (b) In Fitzroy Crossing, all agreed milestones have been met. (c) In Kununurra, all agreed milestones have been met. (2) (a) In Halls Creek, it is anticipated that all agreed milestones will be met. (b) In Fitzroy Crossing, it is anticipated that construction will be completed by January–June 2012. (c) In Kununurra, the building tender has been awarded, with construction anticipated January–June 2012. (d) In Roebourne, it is anticipated that all agreed milestones will be met. (e) In Swan, it is anticipated that all agreed milestones will be met.
(c) In Kununurra, all agreed milestones have been met.
(c) In Kununurra, the building tender has been awarded, with construction anticipated January–June 2012. (d) In Roebourne, it is anticipated that all agreed milestones will be met. (e) In Swan, it is anticipated that all agreed milestones will be met.
(d) In Roebourne, it is anticipated that all agreed milestones will be met. (e) In Swan, it is anticipated that all agreed milestones will be met.
(e) In Swan, it is anticipated that all agreed milestones will be met.