Question regarding land release delays in Hedland, Newman, and Tom Price due to insufficient infrastructure (electricity, water, sewerage). Answer indicates delays in Newman Stage 1 due to electricity supply issues, but no other delays reported by LandCorp or the Department of Regional Development and Lands.

AnsweredQoN 4121Legislative Assembly
Asked
12 October 2010
Portfolio
Regional Development

QuestionView source ↗

What land releases in Hedland, Newman and Tom Price have been delayed or deferred by the absence of sufficient:
(a) electricity supply;
(b) water infrastructure, and
(c) sewerage infrastructure?

AnswerView source ↗

Answered
10 November 2010
Responded by
Minister for Regional Development
Response time
29 days
LandCorp
(a) Newman - titles delayed for Stage 1 - electricity supply.
(b) Nil.
(c) Nil.
The Department of Regional Development and Lands has not experienced any delays or capacity issues to date with the provision of power, water or sewerage infrastructure in Hedland, Newman and Tom Price.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more