Hon Ken Travers questions the allocation of $1 million for the Albany Ring Road project, specifically regarding design, staging, and cost estimation. The Minister provides details on expenditure and completion status.

AnsweredQoN 2934Legislative Council
Asked
25 March 2015
Portfolio
Transport

QuestionView source ↗

I refer to the $1million allocated to advance project development activities for the Albany Ring Road Project, and I ask: (a) how much is being spent on developing a preliminary design for the ultimate dual carriageway scenario; (b) has this work been completed and, if not, when will it be completed; (c) how much is being spent on developing appropriate staging options for the delivery of the project; (d) has this work been completed and, if not, when will it be completed; (e) how much is being spent on the revision of the project cost estimate; and (f) has this work been completed and, if not, when will it be completed?

AnswerView source ↗

Answered
12 May 2015
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
48 days
(a) $690 254.
(b) Yes.
(c) $426 670.
(d) The work is due for completion mid-2015 subject to successful negotiations with the Public Transport Authority and Brookfield Rail for partial use of the rail reserve.
(e) $15 400 and is included in amount outlined in (c).
(f) Yes.