Hon Ken Travers questions the basis for the projected public transport usage figures for the Burswood Stadium project. The response defers answering, citing an incomplete Master Plan.

AnsweredQoN 5273Legislative Council
Asked
8 March 2012
Portfolio
Transport

QuestionView source ↗

In relation to the Burswood Stadium Project, I refer to the recently announced revised figure of 35,500 people travelling to and from events at the stadium, and ask -
(1) How was the new figure of 35,500 people determined?
(2) How many trains would be required?
(3) What modelling was undertaken to ensure the 35,500 people can be achieved?

AnswerView source ↗

Answered
1 May 2012
Responded by
Minister for Finance representing the Minister for Transport
Response time
54 days
The Public Transport Authority advises:
(1 - 3) A Master Plan, will be completed in the first half of 2013. It will include the provisions and cost estimates for road, rail, bus facilities and the pedestrian bridge.
It is assumed the information referred to by the Member relates to statements made in the Legislative Assembly on 22 Feb 2012. The statement was made on advice from the Public Transport Authority and only planned passenger numbers were advised. A Master Plan for this service is being developed and specific information will be made public as appropriate once it has been considered.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more