Question regarding the estimated final cost and completion date of a project, prompted by Auditor General's comments. The Minister provides a specific cost and date.

AnsweredQoN 460Legislative Assembly
Asked
31 August 2005
Portfolio
Planning and Infrastructure

QuestionView source ↗

In view of the Auditor General’s comments, what is now the estimated final cost and completion date? Ms A.J.G. MacTIERNAN

AnswerView source ↗

The estimated final cost is $1.56 billion and the estimated completion date is April 2007.
Ms A.J.G. MacTIERNAN replied: The estimated final cost is $1.56 billion and the estimated completion date is April 2007.
The estimated final cost is $1.56 billion and the estimated completion date is April 2007.