Question seeks detailed cost estimates for overdue maintenance on WA's state road network, including resurfacing, rebuilding, and bridge repairs. The answer refers the member to another question, effectively avoiding a direct response.

AnsweredQoN 814Legislative Council
Asked
23 October 2025
Portfolio
Transport

QuestionView source ↗

I refer to the Main Roads state road network maintenance program, and I ask: (a) what is the most recent Main Roads estimate of: (i) the cost of all overdue resurfacing work; (ii) the cost of all overdue road rebuilding; and (iii) the cost of all overdue work to fix bridges; and (b) in relation to (a), on what date(s) was each figure calculated?

AnswerView source ↗

Answered
2 December 2025
Responded by
Parliamentary Secretary to the Minister for Transport
Response time
7 days
(a)-(b)  I refer the Member to the answer given to Legislative Council Question on Notice 812.