❓ A WA parliamentary question on notice regarding track upgrades and rolling stock for the Australind train line. The answer details spending by the Public Transport Authority and Westnet Rail, and indicates future investigation into new rolling stock.
AnsweredQoN 3357Legislative Assembly
QuestionView source ↗
(2) How much has been spent on track upgrades of the Australind train line since July 1, 2007?
(3) How much is intended to be spent on track upgrades of the Australind train line during:
(a) This financial year – 2007-2008;
(b) 2008-2009 financial year; and
(c) 2009-2010 financial year?
(4) Has the cost of new rolling stock for the Australind been investigated?
(5) If so when, and what was the cost?
(3) How much is intended to be spent on track upgrades of the Australind train line during:
(a) This financial year – 2007-2008;
(b) 2008-2009 financial year; and
(c) 2009-2010 financial year?
(4) Has the cost of new rolling stock for the Australind been investigated?
(5) If so when, and what was the cost?
AnswerView source ↗
Answered
11 June 2008
Responded by
Minister for Planning and Infrastructure
Response time
29 days
Since the privatisation of Western Australia's regional rail network in 2000, responsibility for the maintenance and upgrade of the line used by the Australind rests with the private rail network operator - Westnet Rail - between Mundijong Junction and Picton. The section Mundijong Junction to Armadale is with the Public Transport Authority. The vast majority of traffic on the line used by the Australind is private freight, rather than the Australind passenger service.
(1)
In 2006-07
,
$1.17 million was spent by the Public Transport Authority on resleepering in concrete sleepers between Armadale and Mundijong, and a further $437,335 on upgrading of the signalling and level crossing systems.
(2) Since 1 July 2007, $33,917 has been spent by the Public Transport Authority on upgrading the signalling and level crossing systems.
(3) (a) $33,917 (see answer (2) above).
(b) WestNet Rail advises that it is planning to complete resleepering the railway between Pinjarra and Brunswick between September 2008 and July 2009 at a cost of $54 million.
(c) There is no advice of spending on track upgrades in 2009-10.
(4 & 5) The cost of rolling stock for a new Australind train has not been investigated. It is currently expected that investigation into new rolling stock will commence in about 4 years hence.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
(1)
In 2006-07
,
$1.17 million was spent by the Public Transport Authority on resleepering in concrete sleepers between Armadale and Mundijong, and a further $437,335 on upgrading of the signalling and level crossing systems.
(2) Since 1 July 2007, $33,917 has been spent by the Public Transport Authority on upgrading the signalling and level crossing systems.
(3) (a) $33,917 (see answer (2) above).
(b) WestNet Rail advises that it is planning to complete resleepering the railway between Pinjarra and Brunswick between September 2008 and July 2009 at a cost of $54 million.
(c) There is no advice of spending on track upgrades in 2009-10.
(4 & 5) The cost of rolling stock for a new Australind train has not been investigated. It is currently expected that investigation into new rolling stock will commence in about 4 years hence.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.