Hon Ken Travers questions the Minister for Transport's cost estimate for the Mirrabooka leg of the MAX Light Rail Project. The Minister defers answering, citing the ongoing Project Definition Plan.

AnsweredQoN 1541Legislative Council
Asked
9 September 2014
Portfolio
Transport

QuestionView source ↗

I refer to the Minister’s estimate that the cost of building only the Mirrabooka leg of the MAX Light Rail Project would be "about half – say $1 billion dollars", and I ask: (a) on what basis does the Minister make this claim; (b) does the Minister stand by this estimate; and (c) if no to (b), what does the Minister believe the cost
will now be?

AnswerView source ↗

Answered
14 October 2014
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
35 days
(a-c) The Minister has requested staging options for the project and these will be addressed as part of the Project Definition Plan.