❓ Hon Ken Travers questions the Minister for Transport's cost estimate for the Mirrabooka leg of the MAX Light Rail Project. The Minister defers answering, citing the ongoing Project Definition Plan.
AnsweredQoN 1541Legislative Council
QuestionView source ↗
I refer to the Minister’s estimate that the cost of building only the Mirrabooka leg of the MAX Light Rail Project would be "about half – say $1 billion dollars", and I ask: (a) on what basis does the Minister make this claim; (b) does the Minister stand by this estimate; and (c) if no to (b), what does the Minister believe the cost
will now be?
will now be?
AnswerView source ↗
Answered
14 October 2014
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
35 days
(a-c) The Minister has requested staging options for the project and these will be addressed as part of the Project Definition Plan.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.