Hon Michael Mischin asks about the expected increase in operating subsidy and depreciation costs for the Yanchep rail extension, and requests the business case. The Minister tables a summary project definition plan and states the PTA is reviewing operating parameters.

AnsweredQoN 1016Legislative Council
Asked
30 October 2018
Portfolio
Transport

QuestionView source ↗

JOONDALUP RAIL LINE —
YANCHEP EXTENSION
1016. Hon MICHAEL MISCHIN to the minister representing the
Minister for Transport:
I refer to the Yanchep rail line
extension.
(1) What is the
expected increase in the annual operating subsidy required by the Public
Transport Authority for each year for five years after the completion of the
Yanchep rail extension?
(2) What is the
expected annual depreciation cost each year for five years after the completion
of the Yanchep rail extension?
(3) Will the minister table the
business case; and, if not, why not?

AnswerView source ↗

I thank the honourable member for
some notice of the question.
(1)–(2) The
Public Transport Authority is currently reviewing operating parameters for the
Yanchep rail extension.
(3) I table the attached summary
project definition plan.
[See paper 2115.]