❓ Hon Ken Baston inquires about the status of the Carnarvon police and justice complex construction tender. The Minister responds that a tender has not been accepted and the project is in the site acquisition and scope definition phase, expected to be completed in the second half of 2008.
AnsweredQoN 368Legislative Council
QuestionView source ↗
CARNARVON POLICE AND JUSTICE COMPLEX
I refer to the Carnarvon police and justice complex. (1) Has a tender for the construction of the complex been accepted; and, if yes, when was it accepted and when is its construction due to commence? (2) If no, when will the tender documents be available? Hon JON FORD
I refer to the Carnarvon police and justice complex. (1) Has a tender for the construction of the complex been accepted; and, if yes, when was it accepted and when is its construction due to commence? (2) If no, when will the tender documents be available? Hon JON FORD
AnswerView source ↗
I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
(1) Has a tender for the construction of the complex been accepted; and, if yes, when was it accepted and when is its construction due to commence? (2) If no, when will the tender documents be available? Hon JON FORD replied: I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
(2) If no, when will the tender documents be available? Hon JON FORD replied: I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
Hon JON FORD replied: I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
(1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
(2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
(1) Has a tender for the construction of the complex been accepted; and, if yes, when was it accepted and when is its construction due to commence? (2) If no, when will the tender documents be available? Hon JON FORD replied: I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
(2) If no, when will the tender documents be available? Hon JON FORD replied: I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
Hon JON FORD replied: I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
I thank Hon Ken Baston for some notice of the question. The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
The Minister for Police and Emergency Services has supplied the following answer. (1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
(1) No. (2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
(2) The project site acquisition and scope definition, including a procurement program, is currently underway. It is anticipated that this phase will be completed in the second half of 2008.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.