Hon Robin Chapple asks about a proposed Kalgoorlie-Boulder tourist railway loopline, seeking clarification on a DOLA letter, a concept plan, and specific issues needing to be addressed. The Minister tables the concept plan and identifies alignment and costs as key issues.

AnsweredQoN 266Legislative Council
Asked
13 November 2002
Portfolio
Planning and Infrastructure

QuestionView source ↗

I refer to a letter which I understand is dated August 7 2002 reference 3575/1899V2 and 2746/974V2 (Job No. 022245) signed by T Thomson, Team Leader, South East Region, Land Administration Services from the Department of Land Administration (DOLA) titled ‘Proposed Kalgoorlie-Boulder Tourist Railway Loopline to Hannan Street’ -
(1) Is it correct that part of this letter states ‘The purpose of this plan is to show the proposal in relation to the bypass and intersecting roads and for stakeholders to further consider the proposal in relation to issues that need to be addressed’?
(2) If no to (1), what does the letter state?
(3) Will the Minister table a copy of the concept plan showing the proposed railway corridor 10 metres wide and suggested route which is to terminate in the general area of Hannan Street?
(4) If no to (3), why not?
(5) Can the Minister state what DOLA considers are the specific issues that need to be addressed?
(6) If no to (5), why not?

AnswerView source ↗

Answered
12 December 2002
Responded by
Parliamentary Secretary representing the Minister for Planning and Infrastructure
Response time
29 days
2. Not applicable. 3. Yes. Please refer to Concept Plan (November 2002), tabled as requested. See tabled paper. 4. Not applicable. 5. The Department of Land Administration considers that the specific issues to be addressed are the final alignment of the loopline railway and costs. 6. Not applicable.
3. Yes. Please refer to Concept Plan (November 2002), tabled as requested. See tabled paper. 4. Not applicable. 5. The Department of Land Administration considers that the specific issues to be addressed are the final alignment of the loopline railway and costs. 6. Not applicable.
4. Not applicable. 5. The Department of Land Administration considers that the specific issues to be addressed are the final alignment of the loopline railway and costs. 6. Not applicable.
5. The Department of Land Administration considers that the specific issues to be addressed are the final alignment of the loopline railway and costs. 6. Not applicable.